Make a Gantt chart right on the slide
A project plan as its own slide content: enter tasks, drag them with the mouse, link dependencies. Successors move along, and the chart stays editable until you export it.
What it does
- Tasks, rows, milestones
- Each row holds tasks with day-level dates. Available types are bar, milestone, arrow, bracket and shading.
- Dependencies with lag
- Finish to start, start to start, finish to finish and start to finish, each with a lag in days. With “Move successors when dates change”, dependent tasks follow.
- Drag instead of typing
- Move bars with the mouse or a finger and stretch them at either end. Each gesture is one undo step; arrow keys move by a day, Shift plus arrow changes the length.
- Progress and status
- For the selected task you can set progress in steps of ten and a status: not started, on track, at risk or blocked.
- Baseline and calendar
- Baseline dates show how far the plan has moved from the original. Weekend days, the first day of the week and the start of the fiscal year are configurable.
- Data sheet and paste from spreadsheets
- All rows are also listed in a table with task, responsible, note and status. Up to 1,000 tasks can be pasted from a spreadsheet.
When a Gantt chart belongs on a slide
A Gantt chart shows tasks as bars on a timeline. At a glance you see what happens when, what runs in parallel and which step waits for which. The format goes back to Henry Gantt, who popularised it around 1910 to 1915; Karol Adamiecki had developed a similar “harmonogram” as early as 1896.
On a slide, different things matter than in planning software. The audience needs to take in phases, dependencies and the next milestone, not every resource. If you paste the plan as a picture from another program, it’s hard to change shortly before the meeting. So in Slides the Gantt chart is slide content of its own that stays editable until you export.
For hundreds of tasks with staffing, project management software is still the right tool. For the plan you present and discuss, the Gantt chart in your deck is enough.

How a Gantt chart is built in Excel and PowerPoint
Excel has no Gantt chart type of its own, as Microsoft states in its own guide. The usual route is a stacked bar chart with two series: start date and duration. The start series is made invisible with “Shape Fill > No Fill”, so only the duration remains as a floating bar. Then you reverse the category order and set the minimum of the date axis to the project start.
That works for simple plans but has limits: there are no dependencies, milestones have to be rebuilt as an extra series or shape, and if you move a date, you have to shift every successor yourself. In PowerPoint the result is usually inserted as an Excel chart or a picture. People who build a lot of project slides therefore often turn to add-ins.
In Slides, the Gantt chart is a content type of its own with day-level dates, rows and relationships. There’s no helper series, and the timeline with months and calendar weeks follows from the plan’s start and end.
The four dependency types, explained
Finish to start (FS) is the usual case: B starts when A is done, such as “print after sign-off”. Start to start (SS) means B may begin once A has begun, like taking notes alongside interviews. Finish to finish (FF) ties the endings together: training can’t finish before testing does.
Start to finish (SF) is rare: B may only finish once A has started, typical for shift handovers. Each type can carry a lag in days, positive for a wait, negative for an overlap. Project management calls these gaps lag and lead.
In Slides you create dependencies in the “Gantt data” dialog: predecessor, successor, type and “Lag (days)”. On the slide it works directly too: hold Shift and drag from one task to another. A self-reference, a duplicate or a loop is rejected.


The data sheet: enter exact values
Dragging on the slide is quick; for fixed dates the data sheet is more precise. “Edit Gantt data” opens a dialog with title, start and the first day after the end, then scales (year, quarter, month, week, day), first day of the week, fiscal year and the weekdays shaded as weekends.
The end date is exclusive: a plan that runs through 28 March ends on 29 March. That may seem unusual, but it avoids the classic confusion over whether the last day counts. The duration in days follows without any arithmetic.
The expandable data sheet lists all rows as a table with task, responsible, note and status. If the plan already lives in a spreadsheet, copy rows with task, start (YYYY-MM-DD) and duration in days; owner and note are optional. “Paste tasks from a spreadsheet” takes up to 1,000 tasks and reports incomplete rows by row number.
Common mistakes on Gantt slides
Too many rows: from around 30 tasks, the text on a slide gets very small. In a test with 30 tasks it stayed at 6.5 pt or more. If you need to show more, group tasks into phases or spread the plan over several slides.
The wrong time resolution: a one-year plan on a day scale is unreadable, and a two-week plan on a quarter scale says nothing. Pick two scales, such as month and week, and keep the day scale for short plans.
Dependencies only in your head: if steps aren’t linked, tasks quietly overlap after a change. Linked tasks with “Move successors when dates change” keep the order.
Six styles, from working draft to print
The same plan needs a different look depending on the occasion. The “Gantt style” field offers Standard, Calm, Phases, Consulting, Print and Status. “Calm” uses one accent colour and a quiet grid, “Phases” gives each top-level group its own colour, “Consulting” has a dark header and slim bars for dense slides, “Print” works in greyscale, and “Status” colours by traffic light.
The style changes only the look, not the data. You can maintain a plan in a working style and switch for the meeting. The choice is kept when you reopen it.
Getting it into PowerPoint and LibreOffice
When you save as PPTX or ODP, the Gantt chart is translated into individual shapes: title, timeline, every bar, every milestone. In a test, PowerPoint opened the file without a repair prompt. After ungrouping, a bar could be moved, saved and reopened at its new position.
LibreOffice converts the same file to ODP and keeps shapes and labels. What gets lost are the Gantt rules: in Office they are shapes, not tasks with dependencies. The dialog says so right below the preview. If you want to keep planning later, keep the .bslides file.
One plan for Slides, Documents and Reports
The Gantt chart comes from a building block shared across the suite. The same data sheet with task, owner, note, task type, start, end and duration exists in Slides, Documents and Reports.
In Documents, a plan can also be bound to a published dataset, such as a task list from Sheets. Refreshing keeps the styling and baseline; your own edits to the plan block the refresh so nothing gets overwritten. In Word and ODT files, the Gantt chart appears as a data table, not a chart.
How it works
Insert a Gantt chart
Choose “Insert Gantt chart” in the toolbar. A small starter plan for the current month appears on the slide.
Set the period and scales
Open “Edit Gantt data”, enter the title, start and first day after the end, and pick, say, Month and Week under “Scales”.
Enter the tasks
Build the plan step by step with “Add row” and “Add task”, or use “Paste tasks from a spreadsheet”. Choose milestones via the type, or add them on the slide with “Add milestone”.
Link dependencies
Under “Dependencies”, use “Add dependency” to choose predecessor, successor, type and lag, or hold Shift on the slide and drag from task to task. Turn on “Move successors when dates change”.
Fine-tune on the slide
Drag bars or move them a day at a time with the arrow keys. “Apply” turns each dialog change into one undo step.
Pick a style and export
Pick one of the six styles under “Gantt style”. Saved as PPTX or ODP, every bar arrives in PowerPoint or LibreOffice as a separately editable shape; PDF and PNG work too.
At a glance
- Dependency types
- FS, SS, FF, SF with lag
- Scales
- Year, quarter, month, week, day
- Paste from spreadsheet
- up to 1,000 tasks
- Export
- PPTX, ODP, PDF, PNG
- Also in
- Documents, Reports
- Tested with
- 30 tasks, text ≥ 6.5 pt
Limits
What the feature can’t do yet, or what hasn’t been tested.
- PowerPoint opens the shapes and lets you edit them, but doesn’t read them back as Gantt data. Dependencies are kept only in the .bslides file.
- The Gantt chart is built and checked with automated tests and trials in PowerPoint and LibreOffice, but it isn’t in a released version of Slides yet. A visual check of dense plans in PowerPoint is still pending.
- No resource planning or people workload. The Gantt chart is meant for slides, not as project management software.
- Larger touch handles at the bar ends are still missing.
Frequently asked questions
Can I keep editing the Gantt chart in PowerPoint?
Yes, as shapes: every bar, milestone and label can be moved and changed individually in PowerPoint. To edit it as a Gantt chart with dependencies, keep working in Slides.
Does Excel have a Gantt chart type?
No, Excel has no predefined Gantt chart type. Microsoft describes a workaround with stacked bars in which the start series is made invisible. That workaround has no dependencies.
Do I need think-cell or an add-in?
No. The Gantt chart is built into Slides, as are waterfall and Mekko charts. Slides is free and needs no account.
Can I bring in a plan from Excel?
Yes. Copy the rows with task, start in YYYY-MM-DD format and duration in days, then choose “Paste tasks from a spreadsheet” in the Gantt data. Owner and note can come along as extra columns.
Why is the end date the first day after the end?
It makes it unambiguous whether the last day counts. A task from 4 January through 15 January ends on 16 January and lasts twelve days.
How many tasks fit on one slide?
A plan with 30 tasks was tested; the smallest text was 6.5 pt. For a deck shown to an audience, 10 to 15 rows are easier to read.
When will the feature be available?
The Gantt chart is built and ships with the next released version of Slides. There’s no fixed date yet.